Exusia Digital

Projects

What we are building, and how far along it is.

Three projects at three different stages. We publish the milestone position of each rather than describing them all as imminent, because a portfolio you can see the shape of is worth more than three that all claim to be about to start.

Delta State, associated gas

Ughelli Modular Site

Evidence tier: In development
Capacity5.5 MW
Power cost$0.042 /kWh
Capex band$18M to 24M
EnergisationQ3 2028

4 of 9 done, next: permits granted in Q3 2027

Lagos, group-owned gas generation

Lagos AI Compute Pilot

Evidence tier: Modelled
Capacity2.0 MW
Power costTo confirm
Capex band$9M to 12M
Energisation2029

1 of 9 done, next: energy source agreed

Location to be confirmed

HPC Research Cluster

Evidence tier: Modelled
CapacityTo confirm
Power costTo confirm
Capex bandTo confirm
Energisation2029

0 of 9 done, next: site identified

The milestone ladder

Nine milestones, identical on every project.

Site identified, energy source agreed, land secured, FEED commenced, permits granted, final investment decision, construction start, energisation, commercial operation. Using the same ladder everywhere is what makes the portfolio comparable, including to us.

Capacity tracker

Every megawatt, labelled by how real it is.

Pipeline is not capacity. We show both, with the stage and the evidence behind each figure.

42 MW identified
0 MW energised today
Energised
0 MW
Evidence tier: ContractedAs at August 2026. Financial model v3
Under construction
0 MW
Evidence tier: PermittedAs at August 2026. Financial model v3
In development
5.5 MW
Evidence tier: In development To be confirmedAs at August 2026. Ughelli phase one
Assessment
36.5 MW
Evidence tier: Modelled To be confirmedAs at August 2026. Financial model v3

To be confirmed The split of the identified pipeline between stages is provisional until management confirms it.

As at August 2026. Updated with each model version. Method and sources on the assumptions page. The method